Update: 4865 South Waterline Project
π§ 4865 South Waterline Project β Progress Update! π§
Weβre making great progress on the 4865 South Waterline Project and wanted to share the latest with our community:
β
By the end of today, we anticipate installing 955 feet of new 12β PVC waterline within the project area
β
4420 W was successfully paved last Tuesday following soil compaction testing
π§ Crews are working to extend the 12β waterline to 4180 West by the end of next week
Β
π Whatβs next:
β’ Returning to 4380 W, 4340 W, & 4300 W to install 8β waterlines
β’ Connecting new lines to the existing system after pressure and bacteriological (bac-t) testing is completed and passed
β’ Final asphalt restoration will take place once all waterline installation is complete
Β
π Projected completion remains early July
Thank you for your continued patience as we upgrade critical infrastructure to better serve our community! π